Planning & Decision Making · Guided Practice
Constructing PERT Charts
10 questions with answers and video solutions. Try each one before revealing the answer.
Task B follows task A and has a duration of days.
Calculate the earliest start time of task B.
Answer
The earliest start time of task B is days.
Task C has an earliest start time of days and a duration of days.
Task D has an earliest start time of days and a duration of days.
Calculate the earliest start time of task E.
Answer
Task D finishes at days.
The forward scan takes the maximum, so the earliest start time of task E is days.
Task C has a duration of days and a latest end time of days.
Task D has a duration of days and a latest end time of days.
Calculate the latest end time of task B.
Answer
From task D: days.
The backward scan takes the minimum, so the latest end time of task B is days.
Answer
Answer
Waiting for the latest of them means taking the maximum.
Answer
The tightest of those deadlines is the minimum.
A: no preceding task, days
B: preceded by A, days
C: preceded by A, days
D: preceded by B and C, days
Carry out a forward scan to find the earliest start time of each task, and state the earliest completion time of the project.
Answer
B: earliest start , finishes at
C: earliest start , finishes at
D: earliest start is the maximum of and , so ; finishes at
The earliest completion time is days.
A company provides a team of workers to re-roof a house.
The table shows the list of tasks required to complete this job, the time required for each task, and the order in which the tasks are to be completed.
| Task | Description | Preceding task | Time (hours) |
|---|---|---|---|
| A | Transport materials to location | None | 3 |
| B | Construct scaffolding | A | 7 |
| C | Remove old tiles | B | 4 |
| D | Take old tiles to recycling site | C | 1 |
| E | Inspect roofing | C | 2 |
| F | Purchase required number of roof tiles | D | 1 |
| G | Replace roofing felt | E | 4 |
| H | Replace roofing tiles | F, G | 6 |
| I | Remove scaffolding | H | 3 |
| J | Clean up | H | 2 |
(a) Complete the PERT chart showing the earliest start time and the latest completion time for each task.
(b) The roofing company works for 9 hours each day on this job. State the minimum number of days that the company will require to complete this job.
(c) Construct a Gantt chart, without float times, for this job.

Answer
(a) Correct forward and backward scan on PERT chart.
Forward scan values:
A: 0, 3
B: 3, 7
C: 10, 4
D: 14, 1
E: 14, 2
F: 15, 1
G: 16, 4
H: 20, 6
I: 26, 3
J: 26, 2
Backward scan values:
I: 26, 3, 29
J: 26, 2, 29
H: 20, 6, 26
F: 15, 1, 20
G: 16, 4, 20
D: 14, 1, 19
E: 14, 2, 16
C: 10, 4, 14
B: 3, 7, 10
A: 0, 3, 3
(b) 4 days
(c) Gantt chart plotted correctly. Critical path A-B-C-E-G-H-I.
In a cooking competition, a contestant has 80 minutes to make a crème brûlée.
There are several tasks that need to be completed to make the crème brûlée. The contestant's timings for each task are shown.
| Task | Description | Preceding task | Time (minutes) |
|---|---|---|---|
| A | heat oven | none | 8 |
| B | gather ingredients and prepare bowls | none | 10 |
| C | whisk egg yolks and sugar | B | 5 |
| D | heat double cream in pan | B | 4 |
| E | add cream to egg yolk mixture | C, D | 2 |
| F | sieve mixture and put into bowls | E | 4 |
| G | put bowls into oven and cook | A, F | 35 |
| H | tidy workspace | F | 12 |
| I | sprinkle caster sugar over each bowl and caramelise | G | 3 |
| J | plate up and serve | I | 5 |
(a) Complete the PERT chart below to allow the contestant to determine the earliest start time and latest completion time for each task.
When the contestant puts the bowls into the oven, they realise the oven has not been heated.
(b) Determine whether they can still finish on time. Give a reason for your answer.
Answer
(a) Completed PERT chart:
(b) Yes, because task A takes 8 minutes and there are 16 minutes to spare (or 72 minutes earliest completion time compared to 80 minutes allowed).
A ship is being repaired. The propeller must be removed for the repair to be carried out. The table shows the list of tasks required to complete this job, the time required for each task, and the order in which the tasks must be completed.
| Task | Description | Preceding task | Duration (hours) |
|---|---|---|---|
| A | Disconnect electrics | none | 2 |
| B | Remove oils from system | A | 12 |
| C | Remove rudder | A | 24 |
| D | Disconnect oil pipes and hoses | A | 8 |
| E | Prepare oil pipes and hoses to be reconnected | D | 4 |
| F | Remove propeller blades | B, C, E | 14 |
| G | Disconnect propeller stern seals | B, C, E | 12 |
| H | Disconnect propeller shaft coupling | B, C, E | 8 |
| I | Remove propeller shaft coupling and internal pipes | F, G, H | 6 |
| J | Take out propeller shaft | I | 8 |
(a) Complete the PERT chart showing the earliest start time and the latest completion time for each task.
(b) Construct a Gantt chart without float times for this job.
(c) Determine the critical path and the minimum time required to complete the job.
During the job there are difficulties disconnecting the propeller shaft coupling (task H).
(d) Determine the maximum time that can be taken to disconnect the propeller shaft coupling without delaying the total completion time of the job.
Answer
(a) Correctly completed forward and backward scans. EST, Duration, LCT:
A: 0, 2, 2
B: 2, 12, 26
C: 2, 24, 26
D: 2, 8, 22
E: 10, 4, 26
F: 26, 14, 40
G: 26, 12, 40
H: 26, 8, 40
I: 40, 6, 46
J: 46, 8, 54
(b) Gantt chart constructed consistently with the task times and dependencies.
(c) Critical path: ACFIJ. Minimum time: 54 hours.
(d) 14 hours.