Planning & Decision Making · Guided Practice

Constructing PERT Charts

10 questions with answers and video solutions. Try each one before revealing the answer.

1
In a PERT chart, task A has an earliest start time of 0\displaystyle 0 and a duration of 4\displaystyle 4 days.
Task B follows task A and has a duration of 6\displaystyle 6 days.
Calculate the earliest start time of task B.
Video solution coming soon
2
Task E cannot begin until both task C and task D are complete.
Task C has an earliest start time of 12\displaystyle 12 days and a duration of 5\displaystyle 5 days.
Task D has an earliest start time of 9\displaystyle 9 days and a duration of 6\displaystyle 6 days.
Calculate the earliest start time of task E.
Video solution coming soon
3
Task B must be finished before both task C and task D can begin.
Task C has a duration of 4\displaystyle 4 days and a latest end time of 20\displaystyle 20 days.
Task D has a duration of 5\displaystyle 5 days and a latest end time of 22\displaystyle 22 days.
Calculate the latest end time of task B.
Video solution coming soon
4
State the three values recorded in each node of a PERT chart.
Video solution coming soon
5
Explain why the forward scan takes the maximum value when a task has more than one preceding task.
Video solution coming soon
6
Explain why the backward scan takes the minimum value when a task is followed by more than one task.
Video solution coming soon
7
A project has the following tasks.
A: no preceding task, 5\displaystyle 5 days
B: preceded by A, 7\displaystyle 7 days
C: preceded by A, 3\displaystyle 3 days
D: preceded by B and C, 4\displaystyle 4 days
Carry out a forward scan to find the earliest start time of each task, and state the earliest completion time of the project.
Video solution coming soon
8
2022 Q2
(6, 1, 3)10 Marks

A company provides a team of workers to re-roof a house.

The table shows the list of tasks required to complete this job, the time required for each task, and the order in which the tasks are to be completed.

Task Description Preceding task Time (hours)
ATransport materials to locationNone3
BConstruct scaffoldingA7
CRemove old tilesB4
DTake old tiles to recycling siteC1
EInspect roofingC2
FPurchase required number of roof tilesD1
GReplace roofing feltE4
HReplace roofing tilesF, G6
IRemove scaffoldingH3
JClean upH2

(a) Complete the PERT chart showing the earliest start time and the latest completion time for each task.

Blank PERT Chart

(b) The roofing company works for 9 hours each day on this job. State the minimum number of days that the company will require to complete this job.

(c) Construct a Gantt chart, without float times, for this job.

Blank Gantt chart grid
9
2023 Q2
(6, 2)8 Marks

In a cooking competition, a contestant has 80 minutes to make a crème brûlée.

There are several tasks that need to be completed to make the crème brûlée. The contestant's timings for each task are shown.

Task Description Preceding task Time (minutes)
Aheat ovennone8
Bgather ingredients and prepare bowlsnone10
Cwhisk egg yolks and sugarB5
Dheat double cream in panB4
Eadd cream to egg yolk mixtureC, D2
Fsieve mixture and put into bowlsE4
Gput bowls into oven and cookA, F35
Htidy workspaceF12
Isprinkle caster sugar over each bowl and carameliseG3
Jplate up and serveI5

(a) Complete the PERT chart below to allow the contestant to determine the earliest start time and latest completion time for each task.

Blank PERT chart

When the contestant puts the bowls into the oven, they realise the oven has not been heated.

(b) Determine whether they can still finish on time. Give a reason for your answer.

10
2024 Q3
(5, 3, 2, 1)11 Marks

A ship is being repaired. The propeller must be removed for the repair to be carried out. The table shows the list of tasks required to complete this job, the time required for each task, and the order in which the tasks must be completed.

Task Description Preceding task Duration (hours)
ADisconnect electricsnone2
BRemove oils from systemA12
CRemove rudderA24
DDisconnect oil pipes and hosesA8
EPrepare oil pipes and hoses to be reconnectedD4
FRemove propeller bladesB, C, E14
GDisconnect propeller stern sealsB, C, E12
HDisconnect propeller shaft couplingB, C, E8
IRemove propeller shaft coupling and internal pipesF, G, H6
JTake out propeller shaftI8

(a) Complete the PERT chart showing the earliest start time and the latest completion time for each task.

PERT chart structure

(b) Construct a Gantt chart without float times for this job.

Gantt chart grid

(c) Determine the critical path and the minimum time required to complete the job.

During the job there are difficulties disconnecting the propeller shaft coupling (task H).

(d) Determine the maximum time that can be taken to disconnect the propeller shaft coupling without delaying the total completion time of the job.