Planning & Decision Making · Guided Practice

Precedence Tables

8 questions with answers. Try each one before revealing the answer.

1
A project has the following tasks.
A: no preceding task, 6\displaystyle 6 hours
B: no preceding task, 4\displaystyle 4 hours
C: preceded by A, 5\displaystyle 5 hours
D: preceded by B, 6\displaystyle 6 hours
E: preceded by C and D, 3\displaystyle 3 hours
State which tasks can be started immediately.
Video solution coming soon
2
A project has the following tasks.
A: no preceding task, 6\displaystyle 6 hours
B: no preceding task, 4\displaystyle 4 hours
C: preceded by A, 5\displaystyle 5 hours
D: preceded by B, 6\displaystyle 6 hours
E: preceded by C and D, 3\displaystyle 3 hours
State which tasks must be finished before task E can start.
Video solution coming soon
3
In a precedence table, a task has no entry in the 'preceding task' column.
Explain what this tells you about the task.
Video solution coming soon
4
A project has the following tasks.
A: no preceding task, 6\displaystyle 6 hours
B: no preceding task, 4\displaystyle 4 hours
C: preceded by A, 5\displaystyle 5 hours
D: preceded by B, 6\displaystyle 6 hours
E: preceded by C and D, 3\displaystyle 3 hours
Calculate the minimum time needed to complete the project.
Video solution coming soon
5
A project has the following tasks.
A: no preceding task, 3\displaystyle 3 hours
B: no preceding task, 5\displaystyle 5 hours
C: preceded by A, 4\displaystyle 4 hours
D: preceded by A, 2\displaystyle 2 hours
E: preceded by B, 6\displaystyle 6 hours
F: preceded by C and D, 3\displaystyle 3 hours
G: preceded by E and F, 2\displaystyle 2 hours
Calculate the minimum time needed to complete the project.
Video solution coming soon
6
A project has the following tasks.
A: no preceding task, 3\displaystyle 3 hours
B: no preceding task, 5\displaystyle 5 hours
C: preceded by A, 4\displaystyle 4 hours
D: preceded by A, 2\displaystyle 2 hours
E: preceded by B, 6\displaystyle 6 hours
F: preceded by C and D, 3\displaystyle 3 hours
G: preceded by E and F, 2\displaystyle 2 hours
State the tasks that lie on the longest route through the project.
Video solution coming soon
7
The tasks in a project have durations totalling 40\displaystyle 40 hours, but the project can be completed in 23\displaystyle 23 hours.
Explain how this is possible.
Video solution coming soon
8
Task F is preceded by tasks C and D.
Task C finishes after 11\displaystyle 11 hours and task D finishes after 14\displaystyle 14 hours.
State the earliest time task F can start, and explain your answer.
Video solution coming soon