Planning & Decision Making · Guided Practice
Precedence Tables
8 questions with answers. Try each one before revealing the answer.
1
A project has the following tasks.
A: no preceding task, hours
B: no preceding task, hours
C: preceded by A, hours
D: preceded by B, hours
E: preceded by C and D, hours
State which tasks can be started immediately.
A: no preceding task, hours
B: no preceding task, hours
C: preceded by A, hours
D: preceded by B, hours
E: preceded by C and D, hours
State which tasks can be started immediately.
Video solution coming soon
Answer
A and B.
Neither has a preceding task, so both can begin at the start of the project.
Neither has a preceding task, so both can begin at the start of the project.
Video solution coming soon
2
A project has the following tasks.
A: no preceding task, hours
B: no preceding task, hours
C: preceded by A, hours
D: preceded by B, hours
E: preceded by C and D, hours
State which tasks must be finished before task E can start.
A: no preceding task, hours
B: no preceding task, hours
C: preceded by A, hours
D: preceded by B, hours
E: preceded by C and D, hours
State which tasks must be finished before task E can start.
Video solution coming soon
Answer
C and D must both be finished.
Task E cannot begin until every one of its preceding tasks is complete.
Task E cannot begin until every one of its preceding tasks is complete.
Video solution coming soon
3
In a precedence table, a task has no entry in the 'preceding task' column.
Explain what this tells you about the task.
Explain what this tells you about the task.
Video solution coming soon
Answer
The task does not depend on any other task.
It can be started straight away, at the beginning of the project.
It can be started straight away, at the beginning of the project.
Video solution coming soon
4
A project has the following tasks.
A: no preceding task, hours
B: no preceding task, hours
C: preceded by A, hours
D: preceded by B, hours
E: preceded by C and D, hours
Calculate the minimum time needed to complete the project.
A: no preceding task, hours
B: no preceding task, hours
C: preceded by A, hours
D: preceded by B, hours
E: preceded by C and D, hours
Calculate the minimum time needed to complete the project.
Video solution coming soon
Answer
Route A, C, E: hours
Route B, D, E: hours
The project cannot finish until the longer route is complete, so the minimum time is hours.
Route B, D, E: hours
The project cannot finish until the longer route is complete, so the minimum time is hours.
Video solution coming soon
5
A project has the following tasks.
A: no preceding task, hours
B: no preceding task, hours
C: preceded by A, hours
D: preceded by A, hours
E: preceded by B, hours
F: preceded by C and D, hours
G: preceded by E and F, hours
Calculate the minimum time needed to complete the project.
A: no preceding task, hours
B: no preceding task, hours
C: preceded by A, hours
D: preceded by A, hours
E: preceded by B, hours
F: preceded by C and D, hours
G: preceded by E and F, hours
Calculate the minimum time needed to complete the project.
Video solution coming soon
Answer
A, C, F, G: hours
A, D, F, G: hours
B, E, G: hours
The minimum time is hours.
A, D, F, G: hours
B, E, G: hours
The minimum time is hours.
Video solution coming soon
6
A project has the following tasks.
A: no preceding task, hours
B: no preceding task, hours
C: preceded by A, hours
D: preceded by A, hours
E: preceded by B, hours
F: preceded by C and D, hours
G: preceded by E and F, hours
State the tasks that lie on the longest route through the project.
A: no preceding task, hours
B: no preceding task, hours
C: preceded by A, hours
D: preceded by A, hours
E: preceded by B, hours
F: preceded by C and D, hours
G: preceded by E and F, hours
State the tasks that lie on the longest route through the project.
Video solution coming soon
Answer
B, E, G.
This route takes hours, longer than either route through A.
This route takes hours, longer than either route through A.
Video solution coming soon
7
The tasks in a project have durations totalling hours, but the project can be completed in hours.
Explain how this is possible.
Explain how this is possible.
Video solution coming soon
Answer
Tasks that do not depend on one another can be carried out at the same time.
The project time is set by the longest chain of dependent tasks, not by the total of every duration.
The project time is set by the longest chain of dependent tasks, not by the total of every duration.
Video solution coming soon
8
Task F is preceded by tasks C and D.
Task C finishes after hours and task D finishes after hours.
State the earliest time task F can start, and explain your answer.
Task C finishes after hours and task D finishes after hours.
State the earliest time task F can start, and explain your answer.
Video solution coming soon
Answer
hours.
Task F needs both C and D to be finished, so it waits for the later of the two.
Task F needs both C and D to be finished, so it waits for the later of the two.
Video solution coming soon