Task Planning & Logistics · Guided Practice

Precedence Tables

10 questions with answers and video solutions. Try each one before revealing the answer.

1
Three tasks must be done one after the other:
A takes 3\displaystyle 3 days, then B takes 5\displaystyle 5 days, then C takes 4\displaystyle 4 days.
Calculate the minimum time to complete all three tasks.
Video solution coming soon
2
Tasks A and B can be done at the same time.
A takes 6\displaystyle 6 hours and B takes 4\displaystyle 4 hours.
Task C takes 3\displaystyle 3 hours and can only start once both A and B are finished.
Calculate the minimum time to complete all three tasks.
Video solution coming soon
3
Task A takes 4\displaystyle 4 days. Tasks B and C both start once A is finished, and can run at the same time.
B takes 6\displaystyle 6 days and C takes 9\displaystyle 9 days.
Task D takes 5\displaystyle 5 days and starts once both B and C are finished.
Calculate the minimum time to complete the project.
Video solution coming soon
4
A project has three possible routes through its network, taking 14\displaystyle 14 days, 17\displaystyle 17 days and 12\displaystyle 12 days.
Write down the minimum time to complete the project.
Video solution coming soon
5
Task A takes 5\displaystyle 5 hours. Tasks B and C start once A is finished and can run at the same time, taking 7\displaystyle 7 hours and 3\displaystyle 3 hours.
Task D takes 4\displaystyle 4 hours and starts once both B and C are finished.
Calculate the minimum time to complete all the tasks.
Video solution coming soon
6
2018 P2 Q9(a)(b)
(1, 2)3 Marks

A factory produces cans of tinned beans.
The table shows the list of tasks and the time taken to complete them.

Task Detail Preceding task Time (seconds)
A Boil beans to cook them C 500
B Put on lid H, E 3
C Blanch dried beans in water None 300
D Attach label I 5
E Put sauce in tin F 2
F Make the sauce None 900
G Put in box D 5
H Put beans in tin A 2
I Cook beans in sauce in tin B 300

(a) Complete the diagram below to show the tasks and times in the boxes.

Precedence diagram structure

The factory manager thinks that the whole process can be completed in less than 25 minutes.

(b) Based on the times given, is the factory manager correct?
Use your working to justify your answer.

7
2021 P1 Q10
(2, 2)4 Marks

Sarah wants to make chilli con carne. The table shows the list of tasks and the time taken for Sarah to complete them.

Activity Description Preceding task Time (minutes)
Aassemble ingredientsnone3
Bchop onionsA5
Cheat pan with oilB2
Dfry onions in panC6
Eadd mince to pan and stirD5
Fopen cans of kidney beans and tomatoesC2
Gdrain kidney beansF1
Hmeasure water into jugG1
Iadd spice mix to waterH2
Jadd spice mix and water to panE,I2
Kadd kidney beans and tomatoes and simmerJ35
Lmicrowave riceJ3
MserveK,L2

(a) Complete the diagram below to show the tasks and times in the boxes.

Activity Network Diagram to complete

(b) Sarah claims she can make this chilli con carne in 55 minutes. Based on the times given, determine if she is correct.

8
2022 P1 Q4
(2, 2)4 Marks

Kieran and Dylan decide to redesign their garden.
There are several tasks that need to be done in order to achieve this.

ActivityDescriptionPreceding taskTime taken
Alay patioI5 hours
Bassemble furnitureA1 hour 30 minutes
Cremove deckingnone6 hours
Dpaint fenceG3 hours
Elay artificial grassI3 hours
Fremove grassnone2 hours
Gbuy all materialsC, F45 minutes
Hplant patio tubsA2 hours 15 minutes
Iroughcast wallD1 hour 45 minutes

(a) Complete the diagram to show the tasks and times in the boxes.

Blank precedence diagram

(b) Based on the times given, calculate the minimum time to complete all of the work.
Give your answer in hours and minutes.

9
2023 P1 Q10
(2, 2)4 Marks

John owns a bike shop and has a team of mechanics who build each new bicycle.

The table lists the tasks that need to be completed and the time required for each task.

Task Detail Preceding task Time (minutes)
A attach bicycle to bicycle clamp stand F 1
B grease pedals A 1
C attach wheels A 7
D put bike on display G, H, I, J 2
E grease saddle post F 1
F remove bicycle frame and parts from box none 2
G insert saddle post into frame and tighten E 1
H install headset A 5
I inflate the tyres C 4
J attach pedals B 3

(a) Complete the diagram below by writing these tasks and times in the boxes.

Blank precedence diagram for the bike building tasks

John thinks that the team of mechanics will have the bike ready within 15 minutes.

(b) Determine if John is correct. Use your working to justify your answer.

10
2025 P1 Q3
(2, 1)3 Marks

A company produced the following table to show all the tasks involved in manufacturing and packaging chocolate eggs.

Activity Description Preceding activity Time (seconds)
AMelt chocolate and stir ingredientsH600
BWrap the eggC, I30
CCool the chocolateD1800
DPour chocolate into egg mouldA105
EConstruct the cardboard boxG60
FPlace wrapped egg into boxB, E45
GPrint cardboardH240
HCollect materials and ingredientsnone120
IPrint foilH180

(a) Complete the diagram below to show the tasks and times.

Incomplete activity network diagram with node H starting

(b) Calculate the minimum time taken to manufacture and package a chocolate egg.